Skip to main content

Energy Backup (M1) Photo Documentation

Comprehensive list installation photo package requirements and photo examples.

Updated over 3 weeks ago

Submission packages include five key sections:

  • Project Site

  • Existing System

  • Electrical

  • Storage

  • System Commissioning (Tesla Only)

M1 requirements are geared toward ensuring key principles of system production, safety, and customer experience.

Project Site Photos

PS1) Any additional context for site conditions/site eligibility (if applicable)

  • Any pre-existing damage or conditions such roof damage, altered satellite dishes, gutters, or other pre-existing damage that may be a workmanship liability in the project work area. Documentation helps protect installers from workmanship claims

Note: Existing system information is crucial to verify that the AC coupled sizing rules set by the OEM are followed. Providing all available photos is recommended, but not required. At a minimum we need to be able to determine what that AC system size is for the existing system.

Battery install crew accessing the roof is not expected or required to provide necessary photos of existing system.

Roof / Mounting System

R1) Complete Array(s) with all modules visible (if available)

  • Satellite imagery β€˜OR’ photo from site

  • Complete Array(s) with all modules visible (if available)

R2) Ground Mounts/Ballasted (if applicable)

  • Ground Mount Equipment mounted

  • Ground Mount Complete Array - Front & Back

  • Ballasted Systems Complete Array Front & Back

R3) Balance of System on Site

  • Close up of existing micro or string inverter model used on site (if available)

  • Inverter / Combiner Photo

  • Equipment pullback, AC Disco (fused), Combiner/Inverter, etc.

Electrical

E1) IQ Combiner Wiring (if applicable)

  • Photo of open combiner box showing complete AC wiring inside of combiner box should be shown, including the breakers from the branch circuits.

E2) AC Disconnects (Fused)

  • Interior wiring and terminations - pull back and close up with legible fuse rating

E3) Sub panels/combiner panels (if applicable)

  • Interior wiring and terminations, close-up of breaker ratings, bus rating & dead-front cover off

E4) Main Breaker Rating

E5) Busbar Rating

  • Panel label with busbar rating clearly legible

E6) Point of Interconnection

  • Pull back photo required

  • Close up of taps or back feed breaker (size clearly legible)

E7) Balance of System (Pullback)

E8) Consumption Meters

  • Photo of consumption meters installed to manufacturer specifications

  • Close up photo of arrows facing the correct direction

Above: Enphase Examples

Above: Tesla Examples

E9) Interconnection Agreement

  • Existing system interconnection agreement with the utility provider

Enphase Encharge (10P photo examples)

  • Close up of serial numbers, model, size; Internal wiring/connections; Battery

  • System Controller Wiring & Deadfront (Gateway); Battery CTs;

  • Battery comms cable terminations and installation must be per manufacturer specifications

  • Photos must clearly show both cable ends terminated (in every component), ensuring the drain wire is landed on one end only

Tesla Powerwall 3 Example photos

  • Close up BUG Internal wiring/connections; Battery CT

  • Close up of battery label & serial numbers, model, and size

  • Battery wiring: terminals and RSD; communication cable at Backup switch

  • Battery Wiring: terminals; communication cable at Battery w/ Drain wire

Solar & Consumption Meters

  • Consumption and Production Meters

    • Consumption CTs need to capture ALL home consumption

    • Solar Production CTs need to capture ALL existing and new energy production (if applicable & product specific - Example: Tesla Powerwall 3 requires Tesla Remote Meter Solar CT for existing solar)

    • Close up photo of arrows facing the correct direction

    • There are no exceptions since the battery performance is reliant on these energy measurements

SC1) Commissioning (Tesla only)

  • Commissioning of the system should be completed prior to leaving the site. System should be fully operational with all devices paired, active communication, reporting production and consumption data including cellular connection signal

  • Tesla screenshots should show 'LightReach' added as partner, inverter & CTs enabled, networking connected to Cellular. Include operations settings page for panel current limit & PCS settings

Did this answer your question?