Installation
Installation is the first major operational milestone. The Certified Developer is signaling to LightReach that installation is physically complete, and accurate documentation has been uploaded.
Installation(M1) Requirements for Energy Back-up system:
Existing System
Confirm if there is an existing solar system on site
Manufacturer type, model & quantity
AC system size (kW)
Photos requirements
PV Array
Satellite imagery 'OR' Photo from site
BOS on site
Equipment pullback
AC Disco (fused), Combiner/Inverter, etc.
System Details
New Battery AC system size (kW)
Sizing guide here
Manufacturer type, model & quantity
Monitoring & System Settings
System maintainer access must be established for all projects regardless of PTO status
Site creation required even if system is not yet commissioned
Permit
Utility Bill
Design Package Documents
Plan Set (Should show existing system details)
Existing System Site Map & Layout (if applicable)
One line / 3 line electrical schematics
Point of Interconnection
OCPD size
Wire schedule
Manufacturer spec sheet
Install Photo Documents
Expected Inspection & PTO dates
Incentive Documents - Not applicable at this time
(SD) System Details & Site Qualification
| Item | What We're Checking For |
SD1 | Contract Details |
|
SD2 | Battery Details |
|
SD3 | Site Qualifying |
|
(A) Administrative
| Item | What We're Checking For |
A1 | Battery Monitoring Portal Site ID |
|
A2 | Permits |
|
A3 | Utility Bill |
|
A4 | Approved Interconnection Agreement |
|
(D) Design Package Documents
| Item | What We're Checking For |
D1 | Planset |
|
(IP) Install Photo Documentation
| Item | What We're Checking For |
IP1 | Project Site | |
IP2 | Existing System |
|
IP3 | Electrical | |
IP4 | Storage | |
IP5 | Commissioning |
|
Activation
Activation is the second operational milestone (M2). This signals to LightReach that the system is complete and active, communicating, and all required documentation has been uploaded.
Activation (M2) Requirements include:
Monitoring & System Settings
State of charge & settings
System operating as 'normal' with no errors
PTO Documentation
Incentive Documents - Not applicable at this time
Conditional Approval / Site Improvement
Any pending MPU & related photos/documents
(A) Administrative
| Item: | What We're Checking For: |
A1 | Battery Monitoring Portal Site ID |
|
A2 | Proof of Permission to Operate |
|
A3 | Utility Bill |
|
A4 | Approved Interconnection Agreement |
|
A5 | Conditional Approval / Site Improvement |
|
All requirements must be satisfied to achieve M1 & M2. Requirements are uniform across our ecosystem, however conditional approvals are M1 approvals which grant leniency to submit certain missing or incomplete items at M2. Conditional approvals are automatically provided where reasonably possible - LightReach does not grant exceptions by request.
May qualify for Conditional approval consideration: Minor missing uploads or basic installation fixes solved with a site visit
Will not qualify for Conditional approval consideration: Code violations, or violations of manufacturer specification, egregious workmanship issues, high submission error rates, etc.